An administrative decision issued under the Construction Law Act that authorizes construction of a building to begin, granted after the local authority reviews the design against zoning rules and technical regulations.

Сфера дії: Польща.

Визначення

A building permit (pozwolenie na budowę) is issued under the Construction Law Act (Prawo budowlane), typically by the starosta or, in cities with county rights, the city president. The applicant must submit a construction design prepared by a licensed architect, confirmation of the right to use the plot, and — where applicable — proof the design conforms to the local zoning plan or an obtained building-conditions decision.

Not every building project needs a full permit: smaller, lower-risk works (such as some single-family houses and outbuildings) can instead go through a simplified notification procedure (zgłoszenie), where construction may start if the authority does not object within a set statutory period. A full permit is required for larger or more complex buildings, including most multi-family residential developments.

Once granted, a building permit becomes final and construction may begin; the permit generally lapses if construction has not started within three years or is interrupted for more than three consecutive years.

Приклади

A developer submits an architect-prepared design along with confirmation the plot conforms to the local zoning plan, and receives a building permit before starting site works.

A homeowner planning a small garage instead uses the simplified notification procedure, since the structure falls under the threshold requiring a full permit.

A buyer of an under-construction house checks that the seller actually holds a valid, unexpired building permit before signing a preliminary agreement.

Як це впливає на купівлю та продаж

A buyer of land intended for development should treat an existing, valid building permit as a meaningful asset — obtaining one from scratch can take months, and a permit that has already lapsed due to construction inactivity effectively resets the process. Sellers offering a plot "with building permit" should be able to show the actual decision, not just describe it.